Situation
During a wet and mild winter part of the cliff failed, blocking the access road to
the beach.
opis
Due to the coastal location and clients' wish to have a life span of over 60 years it
®
was decided to install TECCO G65/3 Stainless. The added benefits of the
®
RUVOLUM design made the process very simple and quick. Ischebeck TITAN
INOX 30/11 soil nails were used. The previous shotcrete works on the sea cliffs
are visually obtrusive and the client wanted a natural finish.
Chroniony Objekt
Systemy
Road, Touristic infrastructure
TECCO ® STAINLESS G65/3
Ochrona przeciwerozyjna
INOX / STAINLESS
zabezpieczona powierzchnia
700 m²
Wysokość skarpy
Nachylenie skarpy
12 m
45 ° - 85 °
środki ochronne
Active slope stabilization
Wystawy
North
Stabilizacja skarp | Great Western Beach, GB
2/6
Great Western Beach after storm and slip.
Slipped material at Great Western Beach.
Rolls of TECCO® STAINLESS G65/3 ready for installation.
Stabilizacja skarp | Great Western Beach, GB
3/6
View from above showing excavator mounted drill rig.
during stabilization works. Such a solution allows
extreme fast and easy installation.
Edge of stabilized area: contrast between TECCO®
STAINLESS and historic shotcrete purely visible.
Vertical seem showing stainless T1 connection clip. All
TECCO® SYSTEM3 elements are available as stainless.
Stabilizacja skarp | Great Western Beach, GB
4/6
TECCO® P33 stainless plate mounted on TITAN 30/11
INOX soil nail with a nut.
Overview of completed site. TECCO® SYSTEM3 stainless,
shotcrete and boundary ropes. Aesthetic advantages
clearly visible.
Stabilizacja skarp | Great Western Beach, GB
5/6
W razie pytań prosimy o kontakt ze specjalistą Geobrugga.
Eberhard Gröner
Project Manager North-West Germany, Regional Manager UK
Phone +41 71 466 81 57
Mobile +41 79 421 17 01
[email protected]
Geobrugg AG
Aachstrasse 11 | 8590 Romanshorn | Szwajcaria
[email protected] | www.geobrugg.com
Ein Unternehmen der Gruppe BRUGG | ISO 9001 zertifiziert
Stabilizacja skarp | Great Western Beach, GB
6/6